Dove Drive Construction Updates

This blog is dedicated to providing information about the reconstruction of Dove Drive. This blog will contain the latest information and updates, as it becomes available. 

Nov 14

Update: November 13, 2019

Posted on November 14, 2019 at 9:49 AM by Sharon Reiter


BLOCKED

DRIVEWAY NOTICE

Please be advised, due to historically low November temperatures, the Contractor has revised plans to pour curb and gutter, sidewalk, and driveways.

  • Pouring of concrete curb & gutter, sidewalk and driveway is now scheduled to begin Monday, November 18.  Please note this schedule is weather-pending.
  • This work will prohibit access to your driveway during concrete placement and curing phase for approximately a week and a half.  Access will be restored after all concrete placement and curing, and the subsequent paving, is completed.
  • Parking in driveways as usual is permitted until Monday. During the concrete placement and curing process, please park your vehicles on side streets (excluding Sioux Dr.) a minimum of 100 feet from the intersection with Dove Drive.
  • Parking on side streets is highly encouraged, but if necessary, parking along Dove Drive from 6 PM to 6 AM is permitted.

We apologize for any inconvenience and thank you for your cooperation during this period of necessary work.

QUESTIONS? Please contact the Village’s consulting engineer, Strand Associates, Inc. engineer Donovan Kilker at 630-200-5979


Nov 08

Update: November 8, 2019

Posted on November 8, 2019 at 4:03 PM by Mike Petrick

BLOCKED

DRIVEWAY NOTICE

Please be advised the contractor performing the Dove Dr. Watermain/Roadway/Sidewalk Reconstruction will begin pouring concrete curb & gutter, sidewalk, and driveway on Dove Drive.

  • Pouring of concrete curb & gutter, sidewalk and driveway is scheduled to begin Monday, November 11.  Please note this schedule is weather-pending.
  • This work will prohibit access to your driveway during concrete placement and curing phase for approximately a week and a half.  Access will be restored after all concrete placement and curing, and the subsequent paving, is completed.
  • During the concrete placement and curing process, please park your vehicles on side streets (excluding Sioux Dr.) a minimum of 100 feet from the intersection with Dove Drive.
  • Parking on side streets is highly encouraged, but if necessary, parking along Dove Drive from 6 PM to 6 AM is permitted.

We apologize for any inconvenience and thank you for your cooperation during this period of necessary work.

Residents on neighboring streets may experience additional vehicles parked in front of their homes during this period.

QUESTIONS? Please contact the Village’s consulting engineer, Strand Associates, Inc. engineer
Donovan Kilker at 630-200-5979.


Nov 04

Update: November 4, 2019

Posted on November 4, 2019 at 5:07 PM by Sharon Reiter

Blocked Driveaway Notice

Please be advised the contractor performing the Dove Dr. Reconstruction project will begin work on the roadway tentatively scheduled on Wednesday, November 6th and will last approximately 1 week, weather permitting. Loss of access to your driveway will be approximately 24 hours depending on the location the Contractor is working. This work will include removal of the existing pavement and paving stone. This work may prohibit access to your driveway during construction hours, 7am-5pm.  Access to each driveway will be restored with stone by the end of each work day.

In order to avoid a conflict with your vehicle not being able to enter/exit your driveway during working hours, please park your vehicles on side streets (excluding Sioux Dr.) a minimum of 100 feet from the intersection with Dove Drive. Please note loss of access to your driveway for future construction of curb and gutter, asphalt paving, and driveway replacement will be provided with separate notices to you. We apologize for any inconvenience and thank you for your cooperation during this period of necessary work.

QUESTIONS? Please contact the Village’s consulting engineer, Strand Associates, Inc. engineers Donovan Kilker at 630-200-5979 between 11/4 to 11/10 and Adam Pellegrini beginning 11/11 at 217-597-9901.